A King commissioned a Castle to be built, he had every worker in the town help build it, so that it would be done as quickly as possible.

The construction schedule went as follows: The foundations took exactly 1/6 of the total construction time. The walls took up the next 1/12 of the construction time. The roof was completed over the next 1/7 of the total construction time. Over the next five days, the windows and doors were placed in the castle. The workers spent half of the construction time building the floors after that was done. After that was done, the next four days were spent digging the moat.
How many days total were spent building the castle?

M

Joined
12 Mar 03
Moves
44411
29 Apr 05

84?

cl
nothing good to say

middletown pa, usa

Joined
15 Apr 05
Moves
4737
29 Apr 05

Originally posted by Daemon Sin
A King commissioned a Castle to be built, he had every worker in the town help build it, so that it would be done as quickly as possible.

The construction schedule went as follows: The foundations took exactly 1/6 of the total construction time. The walls took up the next 1/12 of the construction time. The roof was completed over the next 1/7 of the t ...[text shortened]... ext four days were spent digging the moat.
How many days total were spent building the castle?
108 days I believe......

P
Bananarama

False berry

Joined
14 Feb 04
Moves
28719
29 Apr 05

Originally posted by chuck l
108 days I believe......
I'm with Mephisto - 84 days.

Let "t" be the total construction time. Then:

t/6 + t/12 + t/7 + 5 + t/2 + 4 = t

t(1 - 1/6 - 1/12 - 1/7 - 1/2) = 9

t[(84 - 14 - 7 - 12 - 42)/84] = 9

t = 9 * (84 / 9) = 84

cl
nothing good to say

middletown pa, usa

Joined
15 Apr 05
Moves
4737
30 Apr 05

Originally posted by PBE6
I'm with Mephisto - 84 days.

Let "t" be the total construction time. Then:

t/6 + t/12 + t/7 + 5 + t/2 + 4 = t

t(1 - 1/6 - 1/12 - 1/7 - 1/2) = 9

t[(84 - 14 - 7 - 12 - 42)/84] = 9

t = 9 * (84 / 9) = 84
yep, that's right.....I hate it when I make simple math errors.........grrrrrrrr!!!!